Road Restrictions 7/24/2016

Print Road & Bridge Restrictions     Print Road Restrictions Only

ROAD RESTRICTIONS

Interstate Routes

I-5 MP 10.0 to MP 13.5 NB (Ashland) -- NEW --

Effective April 19, 2016, this section of I-5 northbound will be restricted to 20 feet 00 in. in width. Loads wider than 20 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is September 1, 2016.

I-5 NB MP 11.93 (crossing under railroad bridge - Ashland) -- NEW --

Effective April 19, 2016, I-5 northbound crossing under the railroad bridge at MP 11.93 will be restricted to 16 feet 04 in. in height. Estimated date of completion is September 1, 2016.

I-5 MP 128.92 NB & SB (N Umpqua River Bridge - Roseburg)

Effective May 17, 2016, this section of I-5 will be restricted to 12 feet 06 in. in width from 1/2 hr after sunset to 1/2 hr before sunrise. Estimated date of completion is July 15, 2016.

I-5 MP 154 to MP 163 NB & SB (Anlauf)

Effective January 4, 2016, this section of I-5 will be restricted to 16 feet 00 in. in width. Loads wider than 16 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Beginning May 20, 2016 through September 5, 2016 and November 23, 2016 through January 3, 2017 there will be no restrictions per the following schedule: Monday through Thursday between the hours of 10:00am and 5:00 pm; and no restrictions on the weekends from 10 am Friday through 8 pm Sunday. Estimated date of completion is November 22, 2017.

I-5 MP 156.65 NB & SB (crossing under Cox Rd - Anlauf)

Effective January 4, 2016, this section of I-5 will be restricted to 16 feet 07 in. in height. Beginning May 20, 2016 through September 5, 2016 and November 23, 2016 through January 3, 2017 there will be no restrictions per the following schedule: Monday through Thursday between the hours of 10:00am and 5:00 pm; and no restrictions on the weekends from 10 am Friday through 8 pm Sunday. Estimated date of completion is November 22, 2017.

I-5 MP 161.0 to MP 162.3 NB & SB (Anlauf)

Effective July 6, 2016, all loads over 12 ft wide traveling on I-5 between MP 161-162.3 through the construction zone, must travel with a rear pilot vehicle. The rear pilot vehicle shall prevent traffic from passing the overwidth load at all times. Motor carriers not operating with a rear pilot vehicle on this section of I-5 will be provided free pilot vehicle escort service; vehicles traveling northbound must pull over and stage at MP 155.7, vehicles traveling southbound must pull over and stage at MP 166.3, then call 541-405-6934 and wait for pilot vehicle escort. Motor carriers already operating with a rear pilot vehicle do not need to pull over at the signed staging locations and wait for pilot vehicle escort. Convoying of loads may be allowed on a case-by-case basis for loads that are escorted by ODOT provided pilot vehicles. All trucks traveling on I-5 between MP 161-162.3 must stay in the right lane - passing other vehicles is prohibited. Estimated date of completion is September 15, 2016.

I-5 SB on-ramp from OR38/OR99 EB (Drain)

Effective March 1, 2016, the ramp from OR38/OR99 eastbound to I-5 southbound will be closed. Estimated date of completion is September 30, 2016.

I-5 NB & SB Exit 252 ramps to Kuebler Blvd (Salem)

Effective July 22, 2016 at 9 PM, the I-5 northbound and southbound Exit 252 ramps to Kuebler Blvd will be intermittently closed. Both ramps will not be closed at the same time. The ramps are estimated to re-open by 5 AM on July 25, 2016.

I-5 NB Exit 292A ramp to OR217 NB (Tigard)

Effective July 30, 2016, the ramp from I-5 northbound Exit 292A to OR217 northbound will be intermittently closed per the following schedule: Saturday night at 9 PM through Monday morning at 5 AM. Estimated date of completion is September 5, 2016.

I-5 MP 294 to MP 301 NB & SB (Portland) -- NEW --

Effective August 19, 2016, this section of I-5 will be restricted to 12 feet 00 in. in width between the hours of 9 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 MP 294 to MP 301 NB & SB (Portland) -- NEW --

Effective August 19, 2016, this section of I-5 will be restricted to 14 feet 10 in. in height northbound, and 15 feet 00 in. in height southbound, between the hours of 9 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 NB on-ramp from OR99W (Barbur Blvd) - Portland

Effective July 18, 2016, the ramp from Barbur Blvd (OR99W) northbound to I-5 northbound near Exit 294 will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is July 23, 2016.

I-5 SB on-ramp from Capitol Hwy (Portland) -- NEW --

Effective August 19, 2016, the ramp from Capitol Hwy to I-5 southbound will be intermittently closed per the following schedule: Sunday to Thursday nights between the hours of 9 PM & 5:30 AM, Friday nights between the hours of 9 PM & 8 AM, and Saturday nights between the hours of 9 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 NB on-ramp from Capitol Hwy (Portland) -- NEW --

Effective August 19, 2016, the ramp from Capitol Hwy to I-5 northbound will be intermittently closed per the following schedule: Sunday to Thursday nights between the hours of 9 PM & 5:30 AM, Friday nights between the hours of 9 PM & 8 AM, and Saturday nights between the hours of 9 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 NB Exit 295 ramp to Taylors Ferry Rd (Portland) -- NEW --

Effective August 22, 2016, the ramp from I-5 northbound Exit 295 to Taylors Ferry Rd will be intermittently closed between the hours of 8 PM & 6 AM. Estimated date of completion is August 30, 2016.

I-5 SB Exit 296A ramp to Barbur Blvd/OR99W (Portland) -- NEW --

Effective August 19, 2016, the ramp from I-5 southbound Exit 296A to Barbur Blvd (OR99W) will be intermittently closed per the following schedule: Sunday to Thursday nights between the hours of 8 PM & 5:30 AM, Friday nights between the hours of 8 PM & 8 AM, and Saturday nights between the hours of 8 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 NB on-ramp from Spring Garden Rd (Portland) -- NEW --

Effective August 19, 2016, the ramp from Spring Garden Rd to I-5 northbound will be intermittently closed per the following schedule: Sunday to Thursday nights between the hours of 8 PM & 5:30 AM, Friday nights between the hours of 8 PM & 8 AM, and Saturday nights between the hours of 8 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 SB Exit 296B ramp to Multnomah Blvd (Portland) -- NEW --

Effective August 19, 2016, the ramp from I-5 southbound Exit 296B to Multnomah Blvd will be intermittently closed per the following schedule: Sunday to Thursday nights between the hours of 8 PM & 5:30 AM, Friday nights between the hours of 8 PM & 8 AM, and Saturday nights between the hours of 8 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 NB on-ramp from Multnomah Blvd (Portland)

Effective July 18, 2016, the ramp from Multnomah Blvd to I-5 northbound will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is July 23, 2016.

I-5 NB on-ramp from Multnomah Blvd (Portland) -- NEW --

Effective August 19, 2016, the ramp from Multnomah Blvd to I-5 northbound will be intermittently closed per the following schedule: Sunday to Thursday nights between the hours of 9 PM & 5:30 AM, Friday nights between the hours of 9 PM & 8 AM, and Saturday nights between the hours of 9 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 NB on-ramp from Terwilliger Blvd (Portland) -- NEW --

Effective August 19, 2016, the ramp from Terwilliger Blvd to I-5 northbound will be intermittently closed per the following schedule: Sunday to Thursday nights between the hours of 9 PM & 5:30 AM, Friday nights between the hours of 9 PM & 8 AM, and Saturday nights between the hours of 9 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 NB Exit 299A ramp to OR43 (Macadam Ave) - Portland -- NEW --

Effective August 14, 2016, the ramp from I-5 northbound Exit 299A to OR43 (Macadam Ave) will be closed. Estimated date of completion is August 29, 2016.

I-5 NB Exit 299A ramp to OR43/Macadam Ave (Portland) -- NEW --

Effective August 19, 2016, the ramp from I-5 northbound Exit 299A to Macadam Ave (OR43) will be intermittently closed per the following schedule: Sunday to Thursday nights between the hours of 9 PM & 5:30 AM, Friday nights between the hours of 9 PM & 8 AM, and Saturday nights between the hours of 9 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 SB on-ramp from OR43/Hood Ave (Portland) -- NEW --

Effective August 19, 2016, the ramp from Hood Ave (OR43) to I-5 southbound will be intermittently closed per the following schedule: Sunday to Thursday nights between the hours of 9 PM & 5:30 AM, Friday nights between the hours of 9 PM & 8 AM, and Saturday nights between the hours of 9 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-5 NB Exit 299B to I-405 NB (Portland) -- NEW --

Effective August 19, 2016, the ramp from I-5 northbound Exit 299B to I-405 northbound will be intermittently closed on Friday and Saturday nights between the hours of 10 PM & 9 AM. In addition, the ramp from I-5 northbound to Harbor Dr northbound will be closed during the same time. Estimated date of completion is September 19, 2016.

I-5 SB on-ramp from Harbor Dr (Portland) -- NEW --

Effective August 19, 2016, the ramp from Harbor Dr to I-5 northbound will be intermittently closed per the following schedule: Sunday to Thursday nights between the hours of 10 PM & 5 AM, Friday nights between the hours of 10 PM & 7 AM, and Saturday nights between the hours of 11 PM & 8 AM. Estimated date of completion is September 19, 2016.

I-5 NB on-ramp from OR43 NB (Portland) -- NEW --

Effective August 14, 2016, the ramp from OR43 northbound to I-5 northbound will be closed between the hours of 4 AM & 11 AM for one day only.

I-5 MP 300.26 to MP 300.36 NB (Marquam Bridge - Portland) -- NEW --

Effective August 14, 2016, this section of I-5 northbound will be closed between the hours of 4 AM & 11 AM for one day only.

I-5 SB Exit 300B to OMSI / Oregon City (Portland)

Effective August 6, 2016, the ramp from I-5 southbound Exit 300B to OMSI / Oregon City will be closed between the hours of 10 PM & 6 AM. Estimated date of completion is August 7, 2016.

I-5 MP 301.7 SB (Portland)

Effective August 6, 2016, this section of I-5 southbound will be restricted to 16 feet 00 in. in width between the hours of 10 PM & 6 AM. Estimated date of completion is August 7, 2016.

I-5 SB Exit 302A to Moda Center (Portland)

Effective March 25, 2015, the ramp from I-5 southbound Exit 302A ramp to Moda Center will be restricted to 14 feet 00 in. in width on Sunday to Thursday nights between the hours of 8 PM & 5:30 AM, and on Friday nights between the hours of 8 PM & 8 AM. Estimated date of completion is August 31, 2016.

I-5 SB Exit 302A to Moda Center (Portland)

Effective July 14, 2016, the ramp from I-5 southbound Exit 302A to Moda Center will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is July 18, 2016.

I-5 NB Exit 302C to Greeley St (Portland) -- NEW --

Effective August 14, 2016, the ramp from I-5 northbound Exit 302C to Greeley St will be closed between the hours of 4 AM and 12 noon for one day only.

I-5 MP 307.00 to MP 308.38 NB (Portland)

Effective July 18, 2016, this section of I-5 northbound will be restricted to 12 feet 00 in. in width between the hours of 9:30 PM & 5 AM. Estimated date of completion is July 20, 2016.

I-5 NB on-ramp from Jantzen Beach (Portland)

Effective July 18, 2016, the ramp from Jantzen Beach to I-5 northbound will be closed between the hours of 9:30 PM & 5 AM. Estimated date of completion is July 20, 2016.

I-5 MP 308.38 to MP 308.00 SB (Portland)

Effective July 20, 2016, this section of I-5 southbound will be restricted to 12 feet 00 in. in width between the hours of 9:30 PM & 5 AM. Estimated date of completion is July 22, 2016.

I-5 MP 308.18 NB (Columbia River Bridge - Portland)

Effective July 18, 2016, this section of I-5 northbound will be restricted to 15 feet 03 in. in height between the hours of 9:30 PM & 5 AM. Estimated date of completion is July 20, 2016.

I-84 EB Exit 17 ramp to Troutdale

Effective February 15, 2016, the ramp from I-84 eastbound Exit 17 to Troutdale will be intermittently closed per the following schedule: Sunday to Thursday between the hours of 10 PM & 5:30 AM; Friday between the hours of 10 PM & 7 AM; Saturday between the hours of 10 PM & 8 AM. Estimated date of completion is August 31, 2016.

I-84 WB Exit 17 on-ramp from Troutdale

Effective February 15, 2016, the ramp from Troutdale to I-84 westbound at Exit 17 will be intermittently closed per the following schedule: Sunday to Thursday between the hours of 10 PM & 5:30 AM; Friday between the hours of 10 PM & 7 AM; Saturday between the hours of 10 PM & 8 AM. Estimated date of completion is August 31, 2016.

I-84 MP 17 to MP 32 EB & WB (Troutdale to Multnomah Falls)

Effective June 15, 2016, this section of I-84 will be restricted to 12 feet 00 in. in width per the following schedule: eastbound, between the hours of 7 PM & 7 AM; westbound, between the hours of 8 PM & 8 AM. Estimated date of completion is August 31, 2016.

I-84 EB & WB Exit 18 ramps to/from Jordan Rd (east of Troutdale) -- NEW --

Effective June 8, 2016, the I-84 eastbound and westbound Exit 18 ramps to/from Jordan Rd will be intermittently closed between the hours of 9 PM & 6 AM. Estimated date of completion is August 31, 2016.

I-84 EB Exit 22 to Corbett (east of Troutdale) -- NEW --

Effective June 14, 2016, the ramp from I-84 eastbound Exit 22 to Corbett will be intermittently closed between the hours of 9 PM & 6 AM. Estimated date of completion is August 31, 2016.

I-84 MP 22.1 WB (crossing under Corbett Rd Exit 22)

Effective June 7, 2016, I-84 westbound crossing under Corbett Rd Exit 22 will be restricted to 15 feet 06 in. in height between the hours of 8 PM & 8 AM. Estimated date of completion is August 31, 2016.

I-84 WB Exit 22 to Corbett (east of Troutdale) -- NEW --

Effective June 15, 2016, the ramp from I-84 westbound Exit 22 to Corbett will be intermittently closed between the hours of 9 PM & 6 AM. Estimated date of completion is August 31, 2016.

I-84 EB Exit 25 to Rooster Rock State Park (east of Troutdale) -- NEW --

Effective June 14, 2016, the ramp from I-84 eastbound Exit 25 to Rooster Rock State Park will be intermittently closed between the hours of 9 PM & 6 AM. Estimated date of completion is August 31, 2016.

I-84 MP 24.99 EB (crossing under Rooster Rock Exit 25)

Effective June 7, 2016, I-84 eastbound crossing under Rooster Rock Exit 25 will be restricted to 16 feet 07 in. in height between the hours of 7 PM & 7 AM. Estimated date of completion is August 31, 2016.

I-84 WB Exit 25 to Rooster Rock State Park (east of Troutdale) -- NEW --

Effective June 15, 2016, the ramp from I-84 westbound Exit 25 to Rooster Rock State Park will be intermittently closed between the hours of 9 PM & 6 AM. Estimated date of completion is August 31, 2016.

I-84 EB Exit 28 to Historic Columbia River Hwy/Bridal Veil (east of Troutdale) -- NEW --

Effective June 14, 2016, the ramp from I-84 eastbound Exit 28 to Historic Columbia River Hwy/Bridal Veil will be intermittently closed between the hours of 9 PM & 6 AM. Estimated date of completion is August 31, 2016.

I-84 WB Exit 29 to Dalton Point (east of Troutdale) -- NEW --

Effective June 15, 2016, the ramp from I-84 westbound Exit 29 to Dalton Point will be intermittently closed between the hours of 9 PM & 6 AM. Estimated date of completion is August 31, 2016.

I-84 EB Exit 30 to Benson State Rec Area (east of Troutdale) -- NEW --

Effective June 14, 2016, the ramp from I-84 eastbound Exit 30 to Benson State Rec Area will be intermittently closed between the hours of 9 PM & 6 AM. Estimated date of completion is August 31, 2016.

I-84 MP 45.60 to MP 64.50 EB & WB (Cascade Locks-Hood River)

Effective July 26, 2015, this section of I-84 will be restricted to 19 feet 00 in. in width from Midnight Sunday night to 12 Noon on Fridays. Estimated date of completion is November 30, 2016.

I-84 MP 45.60 to MP 64.50 EB & WB (Cascade Locks-Hood River)

Effective May 1, 2016, this section of I-84 will be restricted to 11 feet 00 in. in width between the hours of 8 PM & 8 AM. Estimated date of completion is October 21, 2016.

I-84 MP 54 to MP 55 EB (Starvation Creek)

Effective April 6, 2016, this section of I-84 eastbound will be restricted to 20 feet 00 in. in width. Estimated date of completion is June 30, 2016.

I-84 MP 62.05 WB (Crossing Under Exit 62/US30 - Hood River)

Effective July 26, 2015, I-84 westbound crossing under Exit 62 (US30) will be restricted to 15 feet 05 in. in height. Estimated date of completion is November 30, 2016.

I-84 MP 63.92 WB (Crossing Under Exit 63/2nd St - Hood River)

Effective July 26, 2015, I-84 westbound crossing under Exit 63 (2nd St) will be restricted to 15 feet 09 in. in height. Estimated date of completion is November 30, 2016.

I-84 MP 70.42 to MP 84.31 EB & WB (west of The Dalles)

Effective June 20, 2016, this section of I-84 will be restricted to 12 feet 00 in. in width on Sunday to Thursday nights between the hours of 7 PM & 7 AM. No restrictions will be in place from 11 AM Friday to 7 PM Sunday. Estimated date of completion is August 31, 2016.

I-84 MP 70.42 to MP 84.31 EB & WB (west of The Dalles)

Effective April 11, 2016, this section of I-84 will be restricted to 19 feet 00 in. in width. No restrictions will be in place from 11 AM Friday to 7 PM Sunday. Estimated date of completion is July 22, 2016.

I-84 EB & WB Exit 76 ramps to/from Rowena (west of The Dalles)

Effective July 25, 2016, the I-84 eastbound and westbound Exit 76 on- and off-ramps to/from Rowena will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is August 31, 2016.

I-84 MP 75.50 to MP 84.31 EB & WB (west of The Dalles)

Effective July 27, 2016, this section of I-84 will be restricted to 16 feet 00 in. in width. No restrictions will be in place from 11 AM Friday to 7 PM Sunday. Estimated date of completion is August 31, 2016.

I-84 EB & WB Exit 82 ramps to/from Columbia Gorge Discovery Center (The Dalles)

Effective July 25, 2016, the I-84 eastbound and westbound Exit 82 on- and off-ramps to/from Columbia Gorge Discovery Center will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is August 31, 2016.

I-84 crossing under River Rd Exit 82 (The Dalles)

Effective April 4, 2016, this section of I-84 will be restricted to 16 feet 10 in. in height eastbound, and 19 feet 09 in. in height westbound. No restrictions will be in place from 11 AM Friday to 7 PM Sunday. Estimated date of completion is August 31, 2016.

I-84 EB & WB Exit 83 ramps to/from W 6th St (The Dalles)

Effective July 25, 2016, the I-84 eastbound and westbound Exit 83 on- and off-ramps to/from W 6th St will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is August 31, 2016.

I-84 EB & WB Exit 84 off-ramps to City Center (The Dalles)

Effective July 25, 2016, the I-84 eastbound and westbound Exit 84 off-ramps to The Dalles City Center will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is August 31, 2016.

I-84 MP 97 to MP 98 EB & WB (east of The Dalles)

Effective July 25, 2016, this section of I-84 will be restricted to 17 feet 00 in. in width between the hours of 7 AM & 7 PM. Estimated date of completion is July 28, 2016.

I-84 MP 202.0 to MP 190.5 WB (west of Pendleton)

Effective July 27, 2016, this section of I-84 westbound will be restricted to 12 feet 00 in. in width between the hours of 6 PM & 6 AM. Estimated date of completion is August 31, 2016.

I-84 MP 203.65 to MP 217.75 EB & WB (Pendleton)

Effective August 10, 2016, this section of I-84 will be restricted to 13 feet 00 in. in width between the hours of 6 PM & 6 AM. Estimated date of completion is September 16, 2016.

I-84 MP 203.65 to MP 217.75 EB & WB (Pendleton)

Effective August 10, 2016, this section of I-84 will be restricted to 17 feet 08 in. in height eastbound, and 17 feet 09 in. in height westbound, between the hours of 6 PM & 6 AM. Estimated date of completion is September 16, 2016.

I-84 EB & WB Exit 207 on- and off-ramps to/from US30 (Pendleton)

Effective August 10, 2016, the I-84 eastbound and westbound Exit 207 on- and off-ramps to/from US30 will be intermittently closed between the hours of 10 PM & 4 AM. Estimated date of completion is September 16, 2016.

I-84 EB & WB Exit 209 on- and off-ramps to/from US395 (Pendleton)

Effective August 10, 2016, the I-84 eastbound and westbound Exit 209 on- and off-ramps to/from US395 will be intermittently closed between the hours of 10 PM & 4 AM. Estimated date of completion is September 16, 2016.

I-84 EB & WB Exit 210 on- and off-ramps to/from OR11 (Pendleton)

Effective August 10, 2016, the I-84 eastbound and westbound Exit 210 on- and off-ramps to/from OR11 will be intermittently closed between the hours of 10 PM & 4 AM. Estimated date of completion is September 16, 2016.

I-84 WB Exit 216 off-ramp to OR331 (east of Pendleton)

Effective August 10, 2016, the I-84 westbound Exit 216 off-ramp to OR331 will be intermittently closed between the hours of 10 PM & 4 AM. Estimated date of completion is September 16, 2016.

I-84 EB Exit 252 ramp to OR244 (west of La Grande)

Effective August 8, 2016, the ramp from I-84 eastbound Exit 252 to OR244 will be closed between the hours of 6 AM & 12 noon. Estimated date of completion is August 8, 2016.

I-84 MP 258.55 EB (west of La Grande)

Effective July 26, 2016, this section of I-84 eastbound will be restricted to 14 feet 00 in. in width. Estimated date of completion is July 26, 2016.

I-84 EB crossing under Clover Creek Exit 278 (east of La Grande)

Effective May 9, 2016, I-84 eastbound crossing under Clover Creek Exit 278 will be restricted to 16 feet 08 in. in height. Estimated date of completion is September 30, 2016.

I-84 MP 285.68 to MP 289.17 EB & WB (North Powder)

Effective April 4, 2016, this section of I-84 will be restricted to 20 feet 00 in. in width. Estimated date of completion is August 5, 2016.

I-84 MP 327 to MP 332 EB & WB (Durkee)

Effective March 21, 2016, this section of I-84 will be restricted to 17 feet 06 in. in width. Loads wider than 17 feet 06 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is November 4, 2016.

I-84 MP 354 to MP 346 WB (west of Ontario)

Effective July 11, 2016, this section of I-84 westbound will be restricted to 12 feet 00 in. in width between the hours of 6 PM & 6 AM. In addition, this section of I-84 westbound will be restricted to 16 feet 00 in. in width between the hours of 6 AM & 6 PM. Loads exceeding these dimensions may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is August 26, 2016.

I-84 MP 347.85 WB (west of Ontario)

Effective July 11, 2016, this section of I-84 westbound will be restricted to 18 feet 09 in. in height. Estimated date of completion is August 26, 2016.

I-205 NB on-ramps from OR43 (West Linn) -- NEW --

Effective August 6, 2016, the ramps from OR43 to I-205 northbound will be closed between the hours of 10 PM & 5:30 AM. Estimated date of completion is August 7, 2016.

I-205 SB Exit 8 ramp to OR43 (West Linn) -- NEW --

Effective August 5, 2016, the ramp from I-205 southbound Exit 8 to OR43 will be closed between the hours of 10 PM & 5:30 AM. Estimated date of completion is August 6, 2016.

I-205 NB Exit 9 ramp to OR99E (Oregon City) -- NEW --

Effective August 6, 2016, the ramp from I-205 northbound Exit 9 to OR99E will be closed between the hours of 10 PM & 5:30 AM. Estimated date of completion is August 7, 2016.

I-205 SB Exit 9 on- and off-ramps to/from OR99E (Oregon City) -- NEW --

Effective August 5, 2016, the I-205 southbound Exit 9 on- and off-ramps to/from OR99E will be closed between the hours of 10 PM & 5:30 AM. Estimated date of completion is August 6, 2016.

I-405 SB ramp to I-5 SB (Portland) -- NEW --

Effective August 19, 2016, the ramp from I-405 southbound to I-5 southbound will be intermittently closed on Friday and Saturday nights between the hours of 10 PM & 9 AM. Estimated date of completion is September 19, 2016.

I-405 SB ramp to I-5 NB (Portland) -- NEW --

Effective August 5, 2016, the ramp from I-405 southbound to I-5 northbound will be closed between the hours of 9 PM & 5 AM. Estimated date of completion is August 7, 2016.

I-405 MP 4.20 to MP 0.77 SB (Portland) -- NEW --

Effective August 14, 2016, this section of I-405 southbound will be closed between the hours of 4 AM and 11 AM for one day only. In addition, the following ramps will be closed during the same time: on-ramp from US26 eastbound to I-405 southbound; on-ramp from US30 eastbound to I-405 southbound; on-ramp from NW Couch St to I-405 southbound; on-ramp from NW Taylor St to I-405 southbound; on-ramp from SW Montgomery St to I-405 southbound; on-ramp from SW 5th Ave to I-405 southbound.

I-405 MP 2.00 to MP 3.32 NB (Portland)

Effective July 29, 2016, this section of I-405 northbound will be restricted to 19 feet 00 in. in width between the hours of 10 PM & 5 AM on the following nights: July 29, 2016; July 30, 2016; August 26, 2016; August 27, 2016. Estimated date of completion is August 28, 2016.

I-405 MP 2.00 to MP 3.32 NB (Portland)

Effective July 29, 2016, this section of I-405 northbound will be restricted to 15 feet 08 in. in height between the hours of 10 PM & 5 AM on the following nights: July 29, 2016; July 30, 2016; August 26, 2016; August 27, 2016. Estimated date of completion is August 28, 2016.

I-405 NB Exit 3 to US30 (Portland)

Effective July 29, 2016, the ramp from I-405 northbound Exit 3 to US30 will be closed between the hours of 10 PM & 5 AM on the following nights: July 29, 2016; July 30, 2016; August 26, 2016; August 27, 2016. Estimated date of completion is August 28, 2016.

I-405 MP 4.2 to MP 3.2 SB (Fremont Bridge - Portland) -- NEW --

Effective August 14, 2016, this section of I-405 southbound will be closed between the hours of 4 AM and 12 noon for one day only. In addition, the following ramps will be closed during the same time: ramp from I-5 northbound to I-405 southbound; ramp from I-5 southbound to I-405 southbound; ramp from Kerby St to I-405 southbound; ramp from I-405 southbound Exit 3 to US30 westbound.

U.S. Routes

US20 MP 16.3 EB & WB (west of Eddyville)

Effective August 1, 2016, this section of US20 will be closed on Saturday to Thursday nights between the hours of 7:30 PM & 5:30 AM. Estimated date of completion is October 31, 2016.

US20 MP 56.6 EB & WB (east of Sweet Home)

Effective August 1, 2016, this section of US20 will be closed. Estimated date of completion is September 27, 2016.

US26 MP 0.94 to MP 0.59 WB (Ross Island Bridge - Portland) -- NEW --

Effective August 14, 2016, this section of US26 westbound (Ross Island Bridge) will be closed between the hours of 4 AM & 11 AM for one day only.

US26 EB ramp to OR99E SB (Ross Island Bridge - Portland) -- NEW --

Effective August 14, 2016, the ramp from US26 eastbound (Ross Island Bridge) to OR99E southbound will be closed between the hours of 4 AM & 9:30 AM for one day only.

US26 WB ramp from OR99E NB / Woodward St (Portland) -- NEW --

Effective August 14, 2016, the ramp from OR99E northbound / Woodward St to US26 westbound will be closed between the hours of 4 AM & 11 AM for one day only.

US26 MP 49.20 to MP 57.45 EB & WB (Government Camp)

Beginning April 1, 2016, this section of US26 will be closed for approximately 30 minutes on Mon/Tues/Thurs nights between the hours of 5:30 PM & 6:30 PM. Beginning June 1, 2016, the 30 minute closures will occur between 6:30 PM & 7:30 PM. In addition, there will also be intermittent traffic stops lasting up to 20 minutes at other times during construction work. No construction work will occur on holidays and Sundays. The estimated completion date is September 30, 2016.

US26 EB ramp from NB Cornelius Pass Rd (Hillsboro)

Effective April 1, 2016, the ramp from NB Cornelius Pass Rd to US26 eastbound will be restricted to 16 feet 00 in. in width. Loads wider than 16 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is June 24, 2016.

US30 Bypass WB ramp to/from US30 EB (St John's Bridge - Portland) -- NEW --

Effective August 14, 2016, the ramps to/from US30 Bypass westbound to US30 eastbound will be closed between the hours of 7:30 AM & 12 noon for one day only.

US30 Bypass MP 0.91 EB & WB (St John's Bridge - Portland) -- NEW --

Effective August 14, 2016, this section of US30 Bypass will be restricted to 8 feet 06 in. in width between the hours of 7:30 AM & 12 noon for one day only.

US30 MP 1.97 to MP 3.92 WB (Portland)

Effective June 20, 2016, this section of US30 westbound will be restricted to 14 feet 00 in. in width between the hours of 8 PM & 5 AM. Estimated date of completion is July 29, 2016.

US30 MP 6.51 to MP 13.10 EB & WB (west of Portland)

Effective June 30, 2016, this section US30 will be restricted to 14 feet 00 in. in width. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Loads wider than 14 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is October 31, 2016.

US30 Bypass MP 11.00 to MP 12.00 EB & WB (Portland)

Effective June 17, 2016, this section of US30 Bypass will be restricted to 14 feet 00 in. in width per the following schedule: 7 PM to 6 AM Sunday to Thursday nights; 7 PM to 9 AM Friday nights; 5 PM to 10 AM Saturday nights. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Estimated date of completion is July 22, 2016.

US30 Bypass MP 10.95 to MP 12.10 EB & WB (Portland)

Effective June 17, 2016, this section of US30 Bypass will be restricted to 17 feet 00 in. in width on Monday through Friday between the hours of 9 AM & 2 PM. Estimated date of completion is July 22, 2016.

US30 MP 50.5 to MP 61.0 EB & WB (west of Rainier)

Effective June 19, 2016, this section of US30 will be restricted to 12 feet 00 in. in width on Sunday to Thursday nights between the hours of 6 PM & 6 AM. Estimated date of completion is September 30, 2016.

US30 MP 79.45 to MP 87.75 EB & WB (Knappa)

Effective June 19, 2016, this section of US30 will be restricted to 12 feet 00 in. in width on Sunday to Thursday nights between the hours of 6 PM & 6 AM. Estimated date of completion is September 30, 2016.

US95 MP 20.7 to MP 25.6 NB & SB (Jordan Valley) -- NEW --

Effective August 8, 2016, this section of US95 will be restricted to 14 feet 00 in. in width on Monday through Friday between the hours of 6 AM & 9 PM. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Loads wider than 14 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is August 30, 2016.

US95 MP 57.70 to MP 58.05 NB & SB (Rome) -- NEW --

Effective August 8, 2016, this section of US95 will be restricted to 14 feet 00 in. in width on Monday through Friday between the hours of 6 AM & 9 PM. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Loads wider than 14 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is August 30, 2016.

US97 NB Exit 135A ramp to US20 WB (Bend)

Effective July 11, 2016, the ramp from US97 northbound Exit 135A to US20 westbound will be intermittently closed between the hours of 7 PM & 6:30 AM. Estimated date of completion is July 21, 2016.

US97 MP 141.86 to MP 149.22 NB & SB (south of Bend) -- NEW --

Effective August 15, 2016, this section of US97 will be restricted to 12 feet 00 in. in width on Sunday to Thursday nights between the hours of 7 PM & 7 AM. Estimated date of completion is September 23, 2016.

US97 NB & SB off-ramps to US97 Business (Klamath Falls)

Effective August 1, 2016, the US97 northbound and southbound off-ramps to US97 Business will be intermittently closed on Monday to Thursday between the hours of 6 AM & 4:30 PM. Estimated date of completion is August 11, 2016.

US101 Business MP 6.89 EB & WB (Old Young's Bay Bridge - Astoria)

Effective April 20, 2016, this section of US101 Business will be intermittently closed on Sunday to Thursday nights between the hours of 6 PM & 6 AM. Estimated date of completion is August 5, 2016.

US101 MP 211.21 NB & SB (Umpqua River Bridge - Reedsport)

Effective January 25, 2016, this section of US101 will be restricted to 11 feet 06 in. in width on Monday to Thursday nights between the hours of 7 PM & 7 AM. Estimated date of completion is September 1, 2017.

US101 MP 211.21 NB & SB (Umpqua River Bridge - Reedsport)

Effective January 25, 2016, this section of US101 will be restricted to 14 feet 00 in. in width on Monday to Thursday between the hours of 7 AM & 7 PM. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Loads wider than 14 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is September 1, 2017.

US101 MP 233.99 (McCullough Bridge - Coos Bay)

Effective October 15, 2013, this section of US101 will be restricted to 11 feet 00 in. in width between the hours of 9 PM & 5 AM. Estimated date of completion is November 1, 2018.

US101 MP 311.40 NB & SB (south of Port Orford)

Effective June 14, 2016, this section of US101 will be restricted to 14 feet 00 in. in width. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Estimated date of completion is August 31, 2016.

US101 MP 347.78 NB & SB (Brookings)

Effective June 14, 2016, this section of US101 will be restricted to 14 feet 00 in. in width. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Estimated date of completion is September 23, 2016.

US199 MP 7 to MP 14 NB & SB (south of Grants Pass)

Effective May 23, 2016, this section of US199 will be restricted to 11 feet 00 in. in width on Sunday through Friday from 7 PM to 7 AM. Estimated date of completion is September 16, 2016.

OR Routes

OR8 MP 6.29 to MP 6.99 EB & WB (Aloha)

Effective November 10, 2015, this section of OR8 will be restricted to 14 feet 00 in. in width per the following schedule: Monday to Friday between the hours of 9 AM & 3 PM; Sunday to Thursday nights between the hours of 7 PM & 6:30 AM; Friday and Saturday nights between the hours of 7 PM & 9 AM. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Estimated date of completion is July 29, 2016.

OR22/OR99E Business MP 5.47 to MP 6.20 EB & WB (Salem) -- NEW --

Effective August 13, 2016, this section of OR22/OR99E Business will be closed between the hours of 7:30 AM & 11 AM for one day only.

OR38 MP 0.96 to MP 8.10 EB & WB (east of Reedsport)

Effective July 18, 2016, this section of OR38 will be restricted to 12 feet 00 in. in width. No restrictions will be in place from 3 PM Friday through Sunday. Estimated date of completion is October 31, 2016.

OR38 MP 9.02 to MP 24.63 (near Scottsburg)

Effective July 18, 2016, this section of OR38 will be restricted to 10 feet 00 in. in width. No restrictions will be in place from 3 PM Friday through Sunday. Estimated date of completion is October 31, 2016.

OR38 MP 11.5 to MP 12.5 EB & WB (East of Reedsport)

Effective February 29, 2016, this section of OR38 will be restricted to 14 feet 00 in. in width. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Estimated date of completion is September 15, 2016.

OR38 MP 25.88 to MP 39.06 EB & WB (near Elkton)

Effective June 13, 2016, this section of OR38 will be restricted to 10 feet 00 in. in width. No restrictions will be in place from 3 PM Friday through Sunday. Estimated date of completion is July 18, 2016.

OR38 MP 40.58 to MP 42.59 EB & WB (west of Drain)

Effective June 13, 2016, this section of OR38 will be restricted to 12 feet 00 in. in width. No restrictions will be in place from 3 PM Friday through Sunday. Estimated date of completion is July 18, 2016.

OR43 NB ramp to City Center / I-5 SB / Ross Island Bridge (Portland) -- NEW --

Effective August 14, 2016, the ramp from OR43 northbound to City Center / I-5 SB / Ross Island Bridge will be closed. Estimated date of completion is August 29, 2016.

OR43 MP 6.04 to MP 9.02 NB & SB (West Linn)

Effective October 15, 2014, this section of OR43 will be restricted to 14 feet 00 in. in width. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Estimated date of completion is June 30, 2016.

OR99W MP 8.65 NB & SB (Tigard)

Effective July 29, 2016, this section of OR99W will be restricted to 14 feet 00 in. in width per the following schedule: Monday to Thursday nights between the hours of 8 PM & 6 AM; Friday nights between the hours of 8 PM & 9 AM; Saturday nights between the hours of 8 PM & 10 AM; Sunday nights between the hours of 9 PM & 6 AM. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Estimated date of completion is September 2, 2016.

OR138 (Harvard Ave) MP -0.80 to MP 0.17 EB & WB (Roseburg)

Effective August 12, 2015, this section of OR138 (Harvard Ave) will be restricted to 13 feet 00 in. in width. Loads wider than 13 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permits Unit for information. Estimated date of completion is September 16, 2016.

OR140 MP 25 to MP 35 EB & WB (Bly Mountain)

Effective February 24, 2015, this section of OR140 will be restricted to 12 feet 00 in. in width. Estimated date of completion is December 31, 2016.

OR211 MP 13.5 to MP 16.4 EB & WB (Molalla) -- NEW --

Effective August 29, 2016, this section of OR211 will be restricted to 12 feet 00 in. in width between the hours of 7 AM & 7 PM. Loads wider than 12 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is September 30, 2016.

OR211 MP 26.0 to MP 31.2 EB & WB (Estacada) -- NEW --

Effective August 29, 2016, this section of OR211 will be restricted to 12 feet 00 in. in width between the hours of 8 AM & 7 PM. Loads wider than 12 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is September 30, 2016.

OR213 (NE 82nd Ave) MP 0.94 to MP 1.07 NB & SB (Portland)

Effective May 9, 2016, this section of OR213 (NE 82nd Ave) will be restricted to 14 feet 00 in. in width. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Loads wider than 14 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is August 12, 2016.

OR213 (82nd Ave) MP 3.00 to MP 4.24 NB & SB (Portland)

Effective February 1, 2016, this section of OR213 (82nd Ave) will be restricted to 14 feet 00 in. in width. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Loads wider than 14 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is September 30, 2016.

OR217 SB Exit 2B ramp to Allen Blvd (Beaverton)

Effective July 27, 2016, the ramp from OR217 southbound Exit 2B to Allen Blvd will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is July 30, 2016.

OR217 SB on-ramp from Allen Blvd (Beaverton)

Effective July 27, 2016, the ramp from Allen Blvd to OR217 southbound will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is July 30, 2016.

OR217 SB Exit 3 ramp to Denney Rd (Beaverton)

Effective July 25, 2016, the ramp from OR217 southbound Exit 3 to Denney Rd will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is July 27, 2016.

OR217 SB on-ramp from Denney Rd (Beaverton)

Effective July 25, 2016, the ramp from Denney Rd to OR217 southbound will be intermittently closed between the hours of 10 PM & 5 AM. Estimated date of completion is July 27, 2016.

OR219 MP 33.06 to MP 34.48 EB & WB (west of Woodburn)

Effective July 24, 2016, this section of OR219 will be closed between the hours of 6 AM & 6 PM. Estimated date of completion is July 24, 2016.

OR224 MP 13.65 to MP 13.86 EB & WB (Barton)

Effective June 2, 2016, this section of OR224 will be restricted to 14 feet 00 in. in width between the hours of 8 AM & 4 PM. Mobile homes with eaves are allowed, provided the base width does not exceed 14 feet 00 in. in width. Loads wider than 14 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is September 20, 2016.

OR229 MP 23.79 to MP 23.94 NB & SB (Siletz) -- NEW --

Effective August 13, 2016, this section of OR229 will be closed between the hours of 10 AM & 12 noon for one day only.

OR380 MP 0.08 to MP 0.15 EB & WB (Prineville)

Effective July 25, 2016, this section of OR380 will be restricted to 10 feet 00 in. in width. Estimated date of completion is December 31, 2016.

Lifted Restrictions

I-84 MP 39.82 to MP 40.61 EB & WB (Bonneville Dam)

Effective May 6, 2016, this section of I-84 will be restricted to 14 feet 00 in. in width between the hours of 8 PM & 8 AM. Estimated date of completion is July 15, 2016.

I-84 EB Exit 40 ramp to Bonneville Dam

Effective May 6, 2016, the ramp from I-84 eastbound Exit 40 to Bonneville Dam will be intermittently closed between the hours of 8 PM & 8 AM. Estimated date of completion is July 15, 2016.

I-84 MP 83.96 to MP 88.14 EB & WB (The Dalles)

Effective June 6, 2016, this section of I-84 will be restricted to 12 feet 00 in. in width on Sunday to Thursday nights between the hours of 7 PM & 7 AM. Estimated date of completion is July 15, 2016.

I-84 EB & WB crossing under Brewery Grade Interchange Exit 85 (The Dalles)

Effective November 30, 2015, this section of I-84 will be restricted 16 feet 09 in. in height. Estimated date of completion is July 15, 2016.

I-84 EB & WB crossing under US197 Exit 87 (The Dalles)

Effective November 30, 2015, this section of I-84 will be restricted 16 feet 03 in. in height. Estimated date of completion is July 15, 2016.

I-84 MP 264.5 to MP 265.5 EB & WB (La Grande)

Effective June 13, 2016, this section of I-84 will be restricted to 16 feet 00 in. in width. Loads wider than 16 feet 00 in. in width may be accommodated on a case-by-case basis. Contact the Over-Dimension Permit Unit for information. Estimated date of completion is July 15, 2016.

OR47 MP 34 to MP 35 NB & SB (Yamhill)

Effective July 16, 2016, this section of OR47 will be closed between the hours of 10 AM & 11 AM for one day only.

BRIDGE RESTRICTIONS

Interstate Routes

I-5 MP 104.85 Chadwick Ln crossing over I-5 (near Riddle)

Chadwick Ln crossing over I-5 is restricted to the following weights: 20,000 single axle, 34,000 lbs. tandem axle - 80,000 lbs. GVW. Weight Table 1.

I-5 MP 151.81 Wilson Rd crossing over I-5 (Yoncalla)

Wilson Rd crossing over I-5 is restricted to the following weights: 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2 for divisible loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle, 98,000 lbs. GVW., Weight Table 3 for non-divisible loads.

I-84 MP 256.42 Upper Perry Interchange crossing over I-84 (Perry)

Upper Perry Interchange crossing over I-84 is restricted to the following weights: 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW, Weight Table 2 for divisible loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle - 98,000 lbs. GVW., Weight Table 3 for non-divisible loads.

U.S. Routes

US20 (Corvallis-Newport Hwy) MP 23.38 (Yaquina River Bridge - Eddyville)

Effective May 19, 2006, the Yaquina River Bridge near Eddyville is restricted to the following weights: 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2 for divisible loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle, 98,000 lbs. GVW., Weight Table 3 for non-divisible loads. Vehicles exceeding these weights may cross the bridge if they straddle the centerline, do not exceed 25 MPH and are the only vehicle on the bridge. Certified flaggers are required to stop traffic.

US30 (Historic Columbia River Hwy) MP 0.03 (Sandy River Bridge - Troutdale)

US30 (Historic Columbia River Highway) crossing the Sandy River Bridge is restricted to 30 tons gross weight.

US30 (Huntington Hwy) MP 0.46 (Burnt River Bridge - Lime)

Effective June 16, 2011, the Burnt River Bridge near Lime just off I-84 is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle - 105,500 lbs. GVW., Weight Table 2 for divisible loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle - 98,000 lbs. GVW., Weight Table 3 for non-divisible loads.

US30 (Historic Columbia River Hwy) MP 13.14 (Shepperds Dell Bridge)

US30 (Historic Columbia River Hwy) crossing Youngs Creek (Shepperds Dell) Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, Weight Table 1.

US30 (Historic Columbia River Hwy) MP 17.68 (West Multnomah Falls Bridge)

US30 (Historic Columbia River Hwy) crossing West Multnomah Falls Bridge is restricted to 28,000 lbs. for solo vehicles, 44,000 lbs. for 3-2 combinations, and 56,000 lbs. for 3-3 combinations.

US30 (Historic Columbia River Hwy) MP 20.39 (Horsetail Creek Bridge)

US30 (Historic Columbia River Hwy) crossing Horsetail Creek Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, Weight Table 1.

US30 MP 30.42 (Bridge of the Gods - Cascade Locks)

Effective December 24, 2013, the Bridge of the Gods at US30 MP 30.42 is restricted to 80,000 lbs. GVW, Weight Table 1. This bridge belongs to the Port of Cascade Locks.

US30 OR/WA Border at Rainier (Lewis & Clark Bridge)

The Columbia River (Lewis & Clark) Bridge between Rainier, OR and Longview, WA is restricted to 21,500 lbs. per axle, no gross weight restriction. Contact the State of Washington at (360) 704-6340 for current information regarding size restrictions for this bridge.

US101 Business MP 4.78 (Lewis & Clark River Bridge - Astoria)

US101 Business crossing Lewis & Clark River Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 80,000 lbs. GVW, Weight Table 1.

US101 Business MP 6.89 (Old Youngs Bay Bridge - Astoria)

Effective November 10, 2009, US101 Business crossing the Old Youngs Bay Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW, Weight Table 2.

US101 MP 40.71 (Neahkahnie Mtn Chasm Bridge - near Manzanita)

Effective November 15, 2004, Neahkahnie Mtn Chasm Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2 for divisible loads.

US101 MP 141.67 (Yaquina Bay Bridge - Newport)

Effective March 1, 2013, the Yaquina Bay Bridge in Newport is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle - 105,500 lbs. GVW, Weight Table 2 for divisible loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle - 98,000 lbs. GVW, Weight Table 3 for non-divisible loads. Non-divisible loads exceeding these weights (up to Weight Table 5) may cross the bridge if they stop traffic/straddle the centerline and are the only vehicle on the bridge when crossing. Certified flaggers are required to stop both northbound and southbound traffic. The rolling stop method is not allowed.

US101 MP 190.98 (Siuslaw River Bridge - Florence)

Effective March 17, 2003, the Siuslaw River Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2 for divisible loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle - 98,000 lbs. GVW. Weight Table 3 for non-divisible loads.

OR Routes

OR18 MP 51.57 (Yamhill River Bridge - Dayton)

OR18 crossing Yamhill River Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2 for divisible loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle, 98,000 lbs. GVW., Weight Table 3 for non-divisible loads.

OR22 MP 10.49 (Louie Creek Bridge - Dolph)

OR22 crossing Louie Creek Bridge is restricted to 21,500 lbs. single axle, 43,000 lbs. tandem axle, Weight Table 3 only.

OR22 MP 10.66 (Louie Creek Bridge - Dolph)

OR22 crossing Louie Creek Bridge is restricted to 21,500 lbs. single axle, 43,000 lbs. tandem axle, Weight Table 3 only.

Santiam River Bridge - Mill City (not on OR22 mainline)

1st St crossing Santiam River Bridge in Mill City is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2. This restriction is NOT on the OR22 mainline.

OR27 MP 1.90 (Irrigation Ditch - Prineville)

OR27 crossing Irrigation Ditch at MP 1.90 is restricted to 21,500 lbs. single axle, 43,000 lbs. tandem axle, 60,000 lbs. tri-axle, Weight Table 4.

OR27 MP 2.88 (Irrigation Ditch - Prineville)

OR27 crossing Irrigation Ditch at MP 2.88 is restricted to 21,500 lbs. single axle, 43,000 lbs. tandem axle, 60,000 lbs. tri-axle, Weight Table 4.

OR27 MP 4.62 (Irrigation Ditch - Prineville)

OR27 crossing Irrigation Ditch at MP 4.62 is restricted to 21,500 lbs. single axle, 43,000 lbs. tandem axle, 60,000 lbs. tri-axle, Weight Table 4.

OR27 MP 27.23 (Bear Creek Bridge - south of Prineville)

OR27 crossing Bear Creek Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs GVW, Weight Table 2.

Old OR34 EB MP 0.13 (Willamette River / Van Buren St Bridge - Corvallis)

Old OR34 eastbound crossing Willamette River (Van Buren St) Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 80,000 lbs. GVW., Weight Table 1.

OR35 crossing Columbia River (White Salmon) Bridge - Hood River

OR35 crossing the Columbia River (White Salmon) Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 80,000 lbs. GVW, Weight Table 1. Bridge belongs to Port of Hood River.

OR43 MP 11.43 (Willamette River Arch Bridge - Oregon City)

OR43 crossing the Willamette River Arch Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 80,000 lbs. GVW, Weight Table 1.

OR53 MP 5.98 (Jack Horner Creek Bridge)

OR53 crossing Jack Horner Creek Bridge is restricted to 20,000 lbs. single axle, 40,000 lbs tandem axle, Weight Table 3.

OR99W MP 12.20 SB (Tualatin River Bridge - King City)

OR99W southbound crossing Tualatin River Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2.

OR99 MP 19.09 SB (Ashland Creek Bridge - Ashland)

Effective June 12, 2015, OR99 southbound crossing Ashland Creek Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2. Effective January 14, 2016, 5-axle single unit vehicles will be limited to 58,000 lbs. GVW, 6-axle single unit vehicles will be limited to 64,000 lbs. GVW, 7-axle single unit vehicles will be limited to 72,000 lbs. GVW.

OR104 Spur MP 4.62 (Skipanon River Bridge - Warrenton)

Effective April 4, 2011, OR104 Spur crossing the Skipanon River Bridge is restricted to 38,000 lbs. for solo trucks, 56,000 lbs. for 3-2 axle truck combinations, 64,000 lbs. for 3-3 axle (or more) truck combinations.

OR120 (Swift Hwy / Portland Rd) MP 0.38 (Columbia Slough Bridge - Portland)

OR120 (Swift Hwy / Portland Rd) crossing Columbia Slough Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2.

OR126 Business MP 1.34 WB (Willamette River / Main St Bridge - Springfield)

OR126 Business westbound crossing Willamette River / Main St Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle - 105,500 lbs. GVW., Weight Table 2 for divisible loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle, 98,000 lbs. GVW., Weight Table 3 for non-divisible loads.

OR130 (Little Nestucca Hwy) MP 3.23 (Panther Creek Bridge)

OR130 (Little Nestucca Hwy) crossing Panther Creek Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2.

OR130 (Little Nestucca Hwy) MP 3.60 (Squaw Creek Bridge)

OR130 (Little Nestucca Hwy) crossing Squaw Creek Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2.

OR130 (Little Nestucca Hwy) MP 3.82 (Austin Creek Bridge)

OR130 (Little Nestucca Hwy) crossing Austin Creek Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2.

OR130 (Little Nestucca Hwy) MP 4.15 (Little Nestucca River Bridge)

OR130 (Little Nestucca Hwy) crossing Little Nestucca River Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2.

OR130 (Little Nestucca Hwy) MP 4.76 (Bear Creek Bridge)

OR130 (Little Nestucca Hwy) crossing Bear Creek Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW., Weight Table 2.

OR164 (Jefferson Hwy) MP 6.24 (Santiam River Bridge - Jefferson)

OR164 crossing the Santiam River Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW. Weight Table 2 for divisible loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle, 98,000 lbs. GVW., Weight Table 3 for non-divisible loads.

OR219 MP 23.46 (Willamette River Bridge - south of Newberg)

OR219 crossing Willamette River Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle. 105,500 lbs. GVW., Weight Table 2 for divisible loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle, 98,000 lbs. GVW., Weight Table 3 for non-divisible loads.

OR234 MP 0.04 (Rogue River Bridge - west of Gold Hill)

OR234 crossing Rogue River Bridge west of Gold Hill is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW, Weight Table 2 for divisible Loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle, 98,000 lbs. GVW, Weight Table 3 for non-divisible loads.

OR234 MP 16.01 (Rogue River Bridge - east of Gold Hill)

Effective June 21, 2016, OR234 crossing the Rogue River Bridge is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 80,000 lbs. GVW, Weight Table 1.

OR241 MP 0.51 (Isthmus Slough)

MP 0.51 Isthmus Slough (1/2 mile from US101) is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle - 80,000 lbs. GVW., Weight Table 1

OR339 (Freewater Hwy) MP 2.76 (West Crockett Branch Bridge - Milton-Freewater)

OR339 (Freewater Hwy) crossing West Crockett Branch Bridge is restricted to 21,500 lbs. single axle, 43,000 lbs. tandem axle, 60,000 lbs. tri-axle, Weight Table 4.

OR339 (Freewater Hwy) MP 3.16 (East Fork Little Walla Walla River Bridge - Milton-Freewater)

OR339 (Freewater Hwy) crossing East Fork Little Walla Walla River Bridge is restricted to 21,500 lbs. single axle, 43,000 lbs. tandem axle, 60,000 lbs. tri-axle, Weight Table 4.

OR339 (Freewater Hwy) MP 3.31 (West Fork Little Walla Walla River Bridge - Milton-Freewater)

OR339 (Freewater Hwy) crossing West Fork Little Walla Walla River Bridge is restricted to 21,500 lbs. single axle, 43,000 lbs. tandem axle, 60,000 lbs. tri-axle, Weight Table 4.

Other Jurisdictions

Old OR99 (DC388) Old Winchester Bridge (Roseburg)

Old Winchester Bridge on DC388 (Old 99) at MP12.21 is restricted to 20,000 lbs. single axle, 34,000 lbs. tandem axle, 105,500 lbs. GVW.- Weight Table 2 Divisible Loads; 21,500 lbs. single axle, 43,000 lbs. tandem axle - 98,000 lbs. GVW.- Weight Table 3 Non- Divisible Loads.

Request email notification when restrictions change.